The Ohio State University William Oxley Thompson Library

Location:
Columbus, Ohio

Architects:
Gund Partnership and Acock

Location:
Columbus, Ohio

Architects:
Gund Partnership and Acock

Construction Cost:
$64 million

Project Size:
300,000 SF

Awards:
2009 James B Recchie Design Award
2009 AIA Merit Award with a Special
Citation for Excellence in Architecture
Renovation/Adaptive Use
2011 ACEC Outstanding Achievement Award
2011 AIA/ALA Library Building Award
2013 Boston Society of Architects Design Award

OSU - William Oxley Thompson Library

A unique project for The Ohio State University, the existing building comprises the original structure built in 1913 and an 11-story addition, known as the stacks tower, which was built in 1952. Further, a three-story addition was completed in the mid-1970s, which was demolished to make room for the new four-story addition.

Early in the design process, a seismic analysis of the additions was conducted, and it showed a deficiency in the 1950s addition that resulted in the need for seismic retrofit. Further, primary bearing walls in the original building were removed while maintaining some of the existing framing supported by these walls, resulting in the need for new framing that could support the existing framing. Built over an existing utility tunnel that had to remain in place, some existing foundations were reused to avoid damaging the tunnel.

To achieve the architect’s vision for the project, SMBH had to develop several creative engineering strategies. For example, large portions of bearing walls were removed in the original building to allow for a four-story atrium, which required innovative framing solutions to maintain the existing floors and roof while the supporting walls were removed. Steel plate shear walls were used in the stacks tower so that the presence of new bracing did not reduce the book stack capacity. Understanding the existing structure was crucial to the success of this project. One of the project’s goals was to take a dark and enclosed building, make it open, and bring in daylight. This resulted in numerous requests to SMBH to see if portions of the existing structure could be removed or modified.